INSTALL

Roll
insulation horizontally, starting along the bottom of the
roof.
Batten horizontally between rafters, allowing joint to be
stapled and taped.
Staple every 50mm (Galvanised 14mm staples).
Overlap joints 50-100mm
Cover joint with 100mm ACTIS ISODHESIF tape.
Fix vertical battens ensuring a minimum air gap of 20mm
between the insulation and the membrane.
Fix breathable membrane following manufacturers instructions. TRISO-SUPER
10 Roofing Membrane.
|